I am sure that everyone has been holding their breath and wondering whether all of the wet weather that we have been experiencing in South East Queensland has had a negative impact on our estimated date for Practical Completion. Well, I won’t keep you in suspense any longer. We are happy to inform you that Hindmarsh continues to estimate that the date for Practical Completion is 31 August, 2022. I am sure that this will be a great relief to everyone.
As you can see from our updated photos the eastern end of Building 2 has now caught up to the rest of the building. Although delayed slightly due to the weather, the final pour of concrete occurred on 19 May. The windows and doors have now been fitted throughout the building and, once the tiling of the balconies is completed they will progressively remove the scaffolding.
The site is currently abuzz with tradespeople, finishing the fitout on various levels and appliances are now arriving on site for installation. The building lifts are operational and in the near future the crane will be decommissioned.
Below is are some of the recent milestones:
- Both satellite concrete pumps have been removed
- Main lift core 3 & 4 walls have been poured and the jump structure will be stripped out during the next few weeks
- The main roof slab for the bulk of the building is complete
- Levels 1 to 3, Kitchens and Bathroom Joinery installed, including internal Painting and Tiling
- Apartment internal walls built and being sheeted on levels 4 to 6
Photos Taken Friday 20/05/2022